Maple Crescent Intersection and Road Improvements

Last updated on
Image
Traffic pylons and an arrow sign in a construction zone
Project type
Transportation Development
Project status
Current
Address
Maple Crescent, between 203 Street and 115 Avenue

Maple Crescent will be upgraded at two locations to improve safety and ease of mobility for large vehicles.

Description

Image
Aerial view of the intersection of Hammond Road, Maple Crescent, 203 Street and 113B Avenue
Intersection of Hammond Rd/Maple Cres and 203 St/113B Ave

Hammond Road transitions to Maple Crescent at the intersection where 203 Street transitions to 113B Avenue. This intersection, and the segment of Maple Crescent between 115 Avenue and Westfield Avenue, contain challenging conditions for large vehicles.

Image
Pedestrian island in an intersection
Pedestrian Island in the Intersection

At the intersection of Hammond Road/Maple Crescent and 203 Street/113B Avenue, the northbound right-turn lane will be widened. This will increase the turning clearance for vehicles, specifically large semi trucks that often travel this route. The increased clearance will also increase safety for pedestrians using the sidewalks and pedestrian island.

Image
The s-curve bend in the roadway of Maple Crescent
S-curve along Maple Crescent

Along Maple Crescent, there is an s-curve between 115 Avenue and Westfield Avenue that can be difficult for large vehicles to navigate. At this location, both the east- and westbound lanes will be widened.

Status

Construction is scheduled to begin May 2026 and complete in September 2026.