Kin Park Multi-Use Sports Court

Last updated on
Image
Kin Par - Multi Use Sports Court
Project type
Park Development
Project status
Completed
Address
21790 121 Avenue, Maple Ridge, BC, V2X 6A9

April 2026 - Construction multi-use sports court now complete

Now that the court lines have been installed the construction of the multi-use sports court is complete and ready for some games.

December 2025 - Construction Update

Construction of the Multi-Use Sports Court in Kin Park has now been completed and is open for play. Check it out the next time you are in the neighbourhood.

Please note: that the line painting of the court will be done on a later date once the weather is drier and warmer.

October 2025 - Construction

Construction for the half size multi-use sports court is anticipated to start the third week of October and is expected to be completed in December.
The area of construction and the access road into the park will be closed to the public during this time. 
To view the area that will be closed to the public during construction please see the map at the bottom of this page.

September 2025 - Update

Getting closer to construction. The City has chosen a contractor to construct the half size multi-use sports court, and once details are finalized the work will start. The expected start date is near the end of September with the anticipated completion date to be the middle of December. 

January 2025 - Update

A plan for the new Multi-Sports court is being developed. Thank you for your patience as we continue to work through a regulatory permitting process. Construction of the half size multi-use sports court is anticipated to start once the design and background reporting has been completed.

The baseball diamond and backstop fencing improvements have been deferred at this time.

We will continue to update this page with more information on construction timeline as details are determined. Thank you for your patience. 

October 2023 – What We Heard and Next Steps

Thank you to all who participated in our neighbourhood consultation process that was held this summer. Over the course of the engagement period we received 49 survey submissions.

63% of respondents to the survey indicated that they would like to see a new sports court added to Kin Park. While 61% of respondents agreed with the proposed location shown on the information panels.

While there appears to be a strong interest from the neighbourhood to play basketball at Kin Park and at the proposed location, there were some concerns raised about the size of a full-size sports court at the proposed location and its impact on grass open space.

To support residents request to play basketball in the park while retaining an open grass area for informal use we are proposing to install a half size multi-sport court with basketball and mini hockey goals. The location of the half court is shown below.

We will also be improving the existing baseball field with a new backstop and players benches.

Image
Top view of Kin Park multi-use sports court

July 2023 - Community Engagement

The Maple Ridge Parks, Recreation & Culture department is proposing to install a new full-size multi-use sports court at Kin Park. This is based on the responses that the City received following a survey in November 2022, exploring adding a basketball hoop onto the existing tennis court. 

As part of this process, we have identified a proposed location for a multi-use sports court that minimizes potential tree impacts. Please see the map for location and additional information.

Take the Survey: CLOSED

Please take this survey by September 8, 2023 to have your say on the proposed location for a multi-use sports court at Kin Park.

Attend the Open House

The City will be hosting an open house event on August 17, 2023 from 4:00 PM – 6:00 PM at Kin Park. Please drop-in to talk to staff, ask questions and provide feedback. 

Project Location

21790 121 Avenue