Two segments of the water main on 132 Avenue are being modified.
Description
Upgrades are being made to two segments of the water main on 132 Avenue to improve service for residents.
| Segment | Location | Work |
|---|---|---|
| A | Between 220 Street and 224 Street | The water main is being replaced and the road is being repaved |
| B | Between Balsam Street and 236 Street | A new, additional water main is being installed to support the new 236 Street Pump Station A new telecommunication conduit will also be installed |
Image

Image

Image

Status
Construction is scheduled to begin in mid-October 2026 and will take about seven months to complete.