Culvert Replacements

In 2019, during the annual routine culvert inspections, the Engineering and Engineering Operations Departments identified locations for the replacement of deteriorated culverts at:

104 Avenue:

 100m east of 28269 on 104 Avenue

132 Avenue:

one near the intersection at 220 Street and the other 140m east of 220 Street

The work generally consists of removal of the old corrugated steel pipe culverts and installation of new concrete box culverts as well as the associated management of stream flows, environmental protection and site restoration. The construction has to be done during the Fisheries Window, August 1st to September 15th 2020.

104 Avenue and  132 Avenue are expected to remain open to traffic throughout construction; however there could be short road closures during installation of the box culverts. Any traffic alerts will be posted on the website.

Should you have any questions regarding these projects, you may contact the City of Maple Ridge Project Manager, Velimir Stetin at 604-467-7495.