Road Work and Closures

◄ Back
November 2, 2017 11:00 AM

UPDATE-Full Road Closure-November 2 to December 22 on Fern Crescent Between 128 Ave and 128 Ave East

Full road closure in effect 24 hours and will be open to local and emergency access only. Access to driveways will adjust from east access to west access on Fern Crescent. From Thursday November 2 to Friday December 22, there will be a full road closure on Fern Crescent from 128 Avenue to 128 Avenue (East). The city will be constructing storm and sanitary main infrastructure in effect 24 hours each day. Fern Crescent will be open at all times to local and emergency access only. Access to the driveways will adjust from east access to west access on Fern Crescent as the infrastructure work progresses. Please follow all traffic signs and flaggers as directed around work crews in the work zone. Thank you for your patience.

Facebook Twitter Google Plus Email